Question 5.
Describe two signalling or telecommunication wrong side failures (WSFs) that occur on railway infrastructure. [6 marks]
Explain the possible consequences of each of the WSFs that you have described. [8 marks]
Describe how both procedural and technical solutions can be adopted to minimise the risk of future occurrences of each of the WSFs you have described. [11 marks]


Extremely popular question 6/8 attempts


RE: Q5 Wrongside Failures - PJW - 15-09-2011

(08-09-2011, 10:25 PM)PJW Wrote: [b]Question 5.