Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Approach Locking
#1
One of the (many) task that I have been wanting but not finding the time to do has been to extend my document on Control Tables to include the section on route normalisation.
It certainly seems from the 2004 CTs that more clarity on Comprehensive A/L is needed. I haven't finished it, but in case anyone is wanting to use the Easter period to have a go at some more Control Tables (for example the 2009 i/c/w the Signet event in just over a month's time), I thought it best to post the part which I have now written even though it is incomplete.

Now added a bit more
PJW
Reply
#2
Peter many thanks for this apologies for not being active lately in the forum as have had a rush of projects to finnish for month/quarter end. Will get on with some control tables next week are you suggesting we look at the 2009 layout?
Reply
#3
(03-04-2010, 01:37 PM)merlin89 Wrote: Peter many thanks for this apologies for not being active lately in the forum as have had a rush of projects to finish for month/quarter end. Will get on with some control tables next week are you suggesting we look at the 2009 layout?

Might as well do 2009 next since would co-ordinate with the Signet event on 8th May; suggest all the CTs and a written question.
PJW
Reply


Forum Jump:


Users browsing this thread: 1 Guest(s)